  • Work officially begins to replace Offutt’s aging runway

    OFFUTT AIR FORCE BASE, Neb. -- Work has officially started recently to completely replace Offutt’s aging runway as Phase 0 of the $143.9 million project got underway.Phase 0 consists of a variety of preparatory contractor work prior to the full airfield closure in March 2021 that will help them meet

  • Offutt runway closure delayed 10 months

    The 55th Wing’s runway replacement at Offutt Air Force Base, Nebraska, has been pushed back from December 2019 to October 2020.The ten-month delay of the runway closure allows for demolition and earthwork to begin before winter. This sets up the program to be in the asphalt and concrete work phase